旋喷钻机与高压注浆泵操作规程
1.检查机台布置,钻架及机械安装是否稳固,运轴的方向、角度是否正确。
1. check the layout of the machine, whether the drill and mechanical installation are stable, the direction and angle of the axle are correct.
2.钻机和高压注浆泵各传动部分的保护装置是否装好。
Whether the protective devices of the transmission parts of the 2. drill and the high pressure grouting pump are installed.
3.水泵抽水与排水、排污,是否已妥善解决。
3. pump pumping and drainage, sewage, whether it has been properly solved.
4.检查钻机和高压泵柴油机的机油尺标,油箱应加满油,水箱应加满水;冬季施工气温很低时下班后,应放掉水箱中的存水,以防水箱结冰,造成水箱开裂。
4. check the oil gauge of drilling rig and high pressure pump diesel engine. The tank should be filled with oil and the water tank should be filled with water. When the temperature is very low in winter, the water stored in the tank should be released after work, so as to prevent the water tank from freezing and cause the water tank to crack.
5.钻机合箱螺丝要上紧,运转时不能晃动。
The screw of the 5. rig should be tightened, and it can not shake when it is running.
6.钻机旋喷龙头的丝扣要上牢,严防掉下伤人。
Thread 6. rig jet leading to prison, to prevent the fall wounding.
7.高压泵头连接处软管的防滑链要挂牢靠,以防接头滑丝伤人。
7. the antiskid chain of the hose at the joint of the high pressure pump should be hung firmly in order to prevent the slipping of the joint.
8.运转的机器上,不得放置工具等物。
No tools, such as a tool, can be placed on the 8. operating machine.
9.在试运转正常后,确认机器运转时,各部位碰不到人和其他物件后,才能启动机器开钻或注浆。
9. when the test operation is normal, when the machine is confirmed, the machine can start to open the drill or grouting after the parts are not touched by the people and other objects.
10.工作时必须穿好工作服并扣好衣扣,不能敞胸露怀。
Must wear work clothes and buckle up 10. work, not bare chested.
11.徒工未经允许或无班长在场指导时,不得自行操作钻机。
The 11. apprentice without permission or without the presence of monitor guide, not to operate drill.
12.上钻架时所带工具要栓好,用后要拿下,以防掉下伤人。
12. to drill the tool when the tool should be bolt well, use it after use, in order to prevent the wounded.
13.夜间无照明或照明亮度不足时不能工作。
13. no work at night without lighting or insufficient lighting.
14.钻进时必须将孔内情况、钻进参数、机器运转情况按要求记录下来。
14. drilling must be recorded in the hole, the drilling parameters and the operation of the machine according to the requirements.
15.机器不得超负荷运转,以免损坏机械或伤人。
15. machine must not be overloaded, so as not to damage machinery or to hurt people.
16.柴动高压注浆泵在停工或放置期间,应当断开电瓶线以防止电瓶漏电,并定期启动高压注浆泵补充电瓶电量。
16. firewood high pressure grouting pump during the shutdown or placement, should break off the battery line to prevent the leakage of the battery, and regularly start the high-pressure grouting pump to supplement the battery power.
17.高压注浆泵运转时,操作人员应精力集中,观察仪表各项参数,如水温、机油压力、转速、注浆压力等等是否正常。
17. when the high-pressure grouting pump is running, the operators should concentrate their energy and observe the parameters of the instrument, such as water temperature, oil pressure, speed, grouting pressure and so on.